What is an interim invoice (Abschlagsrechnung)?

An interim invoice requests payment for part of a larger service already performed; the final invoice settles it at the end (§ 632a BGB).

Last updated:

Key takeaways

  • An interim invoice presupposes work done. Whoever has done nothing yet asks for an advance payment, which is something else.
  • Without an agreement § 632a BGB gives the contractor in a work contract a right to interim payments equal to the value of the work performed.
  • For VAT an interim payment is usually an advance: the tax arises on receipt, and the invoice needs every mandatory detail.
  • The final invoice must deduct every interim invoice with number, date and amount, or the client pays twice or not at all.
  • Valtor reads the payment plan from the contract and readies each instalment on its trigger, and you approve every invoice.

What is an interim invoice?

An interim invoice is the invoice for a part payment on a service that is not yet fully performed. It is usual for projects that run for weeks or months: you perform a part, invoice that part, and do not finance the project alone. The sum of all interim payments is never final, but is settled in the final invoice.

In daily use the same invoice is also called a partial invoice, progress invoice or instalment. The words are not protected. All that matters is that the document carries the mandatory details of an invoice and says plainly that it is an interim invoice and which performance it covers.

How do interim, advance payment and final invoices differ?

Three documents settle the same service in stages. Confuse them and VAT and the final settlement go wrong:

Advance payment invoiceInterim invoiceFinal invoice
WhenBefore any performanceAfter a part is performedAfter full performance
BasisContractContract or § 632a BGBWhole service (§ 14 (5) UStG)
AmountAgreed shareValue of the work performedTotal less what is already billed
DueAs the contract saysAs the contract says, else at onceWith acceptance (§ 641 BGB)

When may you demand an interim payment?

The safest route is a contract with a payment plan: instalments by date or milestone, such as 30% on concept approval. Without a payment plan the contractor in a work contract can demand an interim payment equal to the value of the work performed as the contract requires (§ 632a (1) BGB). The work must be evidenced by a statement that allows a quick and reliable assessment.

If the work performed does not conform to the contract, the client may refuse an appropriate part of the interim payment, and until acceptance the burden of proving conforming performance stays with you (§ 632a (1) BGB). A service contract such as a retainer needs no interim payments: it is billed per agreed period anyway, often in advance. VOB/B contracts have their own rules, such as the 21-day period in § 16 (1) no. 3 VOB/B.

How do you calculate the amount of an interim invoice?

There are three usual ways. With a payment plan the instalment is in the contract, say 30% of €60,000 net. With progress you determine the share of the work performed and multiply it by the price. With a milestone the instalment hangs on an event such as acceptance of a phase.

Always calculate from the total price and carry forward: total price, billed so far, this instalment, remainder. Then on every invoice you can see whether the sum of interim payments exceeds the value of the work performed. An interim payment above progress is an advance and should be marked as one.

What must an interim invoice state?

It is a full invoice under § 14 (4) UStG and needs the same details as any other:

  • Name and address of you and the client and your tax number or VAT identification number.
  • Issue date and a consecutive invoice number, assigned once.
  • Quantity and kind of the service, here the part performed with reference to the contract and payment plan.
  • Time of the supply or, for an advance, the time the payment was received if it is certain and differs from the invoice date (§ 14 (4) no. 6 UStG).
  • The fee by tax rate, the rate and the tax amount, and any reduction agreed in advance.
  • The label “interim invoice no. 2” plus billed so far and still open, so the final invoice is right.

How is VAT treated on interim payments?

It depends on what the payment represents. A partial supply exists when an economically distinct part of the work is finished and a separate fee was agreed for it. The tax then arises when the partial supply is performed (§ 13 (1) no. 1 lit. a sentence 3 UStG). An interim payment on a work still unfinished is, for VAT, an advance: the tax arises at the end of the advance-return period in which you receive the money (sentence 4).

In both cases you show VAT if the supply is taxable. On an advance the client may deduct input VAT as soon as it holds the invoice and has paid (§ 15 (1) sentence 1 no. 1 sentence 3 UStG). Where it is doubtful whether there is a partial supply, clarify it with your tax adviser.

When is an interim invoice due, and when does default occur?

The contract governs. If it names a payment term, the term runs from the invoice date or from receipt, depending on the wording. Without an agreement the claim is due immediately on receipt of the invoice (§ 271 BGB), and default occurs at the latest 30 days after due date and receipt (§ 286 (3) BGB).

Whether due date additionally requires acceptance depends on the contract. Interim payments exist precisely to let money flow before acceptance. Whoever does not want that ties the instalment to acceptance and writes it in.

Which mistakes with interim invoices cost money?

  • An instalment is never billed because nobody notices the trigger in the payment plan, and liquidity is missing for months.
  • An instalment is billed twice or deducted twice from the final invoice, because the client cannot follow the number.
  • The invoice does not refer to the payment plan, and the client disputes that it is due yet.
  • The final invoice deducts interim payments as gross instead of net and tax, and the VAT is wrong.
  • The interim payment exceeds progress, the client rightly cuts it, and nobody chases the rest.

The guide on milestone billing shows how a payment plan becomes invoices. Once the client releases the work, acceptance applies, and the last instalment becomes the invoice after full performance.

second instalment of a payment plan

A project of €60,000 net has three instalments: 30% on signing, 30% on concept approval, 40% on acceptance. The first interim invoice of €21,420.00 gross is paid. On 5 November 2026 the client approves the concept.

Interim invoice no. 2: 30% of €60,000.00, concept approvalContract, payment plan
€18,000.00
VAT 19%§ 12 (1) UStG
€3,420.00
Invoice total, gross
€21,420.00

Billed so far: €36,000.00 net. For the final invoice €24,000.00 net and €4,560.00 VAT remain, €28,560.00 together. All three invoices add up to €71,400.00, the gross price of the project.

How Valtor handles this

Valtor bills instalments that the contract ties to a date or a milestone, and lets you check every invoice. Valtor books nothing and picks no account.

Valtor does

  • Reads the payment plan and milestones from the contract, each value with clause and page, and sets up every instalment as an obligation with a date or trigger
  • Prepares the invoice once the date is reached or the trigger is evidenced, and holds an instalment while evidence is missing
  • Shows an agreed retention as a line of its own below the amount earned or only as a note, depending on the setting
  • Creates the invoice as an e-invoice (XRechnung or ZUGFeRD) with a consecutive number
  • Records which clause each amount comes from and writes every change to the audit log

You decide

  • You approve the reading of the contract before instalments enter the calendar
  • You decide with your tax adviser whether an instalment is a partial supply or an advance for VAT
  • You approve and send every invoice

Questions and answers

Is an interim invoice the same as a partial invoice?

In daily use both words mean an invoice for part of the whole service. What matters is that the invoice carries every mandatory detail and the final invoice deducts it.

Must the client pay an interim invoice at once?

The agreed payment term applies. Without one the claim is due immediately (§ 271 BGB), and default occurs at the latest 30 days after due date and receipt of the invoice (§ 286 (3) BGB).

May I demand interim payments without an agreement?

In a work contract yes, equal to the value of the work performed (§ 632a (1) BGB), with a statement that evidences the work. In a service contract payment follows the contract.

Does VAT arise with the invoice or with the payment?

On an advance at the end of the advance-return period in which you receive the money (§ 13 (1) no. 1 lit. a sentence 4 UStG). On a partial supply when it is performed.

What if an interim invoice was wrong?

You do not overwrite it. You correct it with a correction invoice (Rechnungskorrektur) or cancellation invoice (Stornorechnung) that refers to the original.

Can the client cut interim payments?

Yes, an appropriate part if the work does not conform (§ 632a (1) BGB). It may also withhold a part equal to the cost of rectifying defects under § 641 (3) BGB.

How many interim invoices may I issue?

As many as the contract provides and work has been performed. The law sets no number. Each needs its own number and the state of billing so far.

This page is general information, not legal or tax advice. Please ask your tax advisor about your own case.