What is an advance payment invoice (Anzahlungsrechnung)?
An advance payment invoice asks for part of the price before the service is performed, and the final invoice deducts that advance again (§ 14 (5) UStG).
Last updated:
Key takeaways
- An advance is money before performance. An interim payment, by contrast, follows a part already performed.
- The law gives you no right to an advance: you need an agreement in the contract.
- VAT arises on receipt, and the invoice must state the time of payment if it differs from the invoice date.
- The final invoice must deduct the advance together with the tax on it, or your client owes too much VAT.
- Valtor keeps every advance as a document of its own and deducts it only in the final invoice, to the extent it has been paid.
What is an advance payment invoice, and what is it not?
An advance payment invoice asks for money before you have performed the service or any part of it. It secures your upfront effort and is usual when you lay out third-party costs, buy materials or build something custom. In media it occurs when budgets are paid in before the booking.
It is not an interim invoice. There the contractor has already performed a part and bills it. A deposit is not an advance either: it secures claims and is returned, not credited. And “prepayment” usually means paying the whole price before performance, which is a special case of an advance.
| Term | What is performed? | How is it settled? |
|---|---|---|
| Advance | Nothing yet | Deducted in the final invoice |
| Interim payment | Part of the work | Deducted in the final invoice |
| Prepayment | Nothing yet, full price | The final invoice shows the balance |
| Deposit | Nothing | Returned or set off, not treated as fee |
Are you entitled to an advance?
No. The law has the fee paid after performance: in a work contract it falls due on acceptance (§ 641 (1) BGB), in a service contract after the services are rendered (§ 614 BGB). You can demand an advance only if the contract provides for it, with amount and due date.
In your general terms, duties of the client to pay upfront are valid only within narrow limits (§ 307 BGB), because they deviate from the statutory model. Better to agree an advance expressly in the individual contract, with reasons such as the third-party costs you lay out. Further limits apply to consumers, and where you do business with consumers, have the clause reviewed.
What must an advance payment invoice state?
Paragraphs 1 to 4 of § 14 UStG apply accordingly to advances (§ 14 (5) sentence 1 UStG). The invoice therefore needs the same mandatory details as any other, and a note that it is an advance:
- Names and addresses, your tax number or VAT identification number, the issue date and a unique, consecutive invoice number.
- Quantity and kind of the future service, precise enough to tie the advance to the contract.
- The time the payment was received, if certain and different from the invoice date (§ 14 (4) no. 6 UStG), otherwise a statement that it is still open.
- The fee by tax rate, the rate and the tax amount on the advance.
- The label “advance payment invoice” and the total price, so the client sees the remainder.
When does VAT arise on an advance?
If the fee or part of it is received before the service is performed, the tax arises to that extent at the end of the advance-return period in which you receive the money (§ 13 (1) no. 1 lit. a sentence 4 UStG). You therefore pay the tax over earlier than on performance. If you do not receive it, nothing arises. The advance payment invoice alone does not trigger the tax.
Your client may deduct input VAT on the advance once it holds the invoice and has paid (§ 15 (1) sentence 1 no. 1 sentence 3 UStG). It needs an invoice with separately shown tax for that. Without one the input VAT waits until the final invoice. That is why clients ask for it.
How do you settle the advance in the final invoice?
If a final invoice is issued after performance although you received advances, it must deduct the partial fees received before performance and the tax on them, where invoices under paragraphs 1 to 4 were issued for them (§ 14 (5) sentence 2 UStG). The final invoice therefore shows the full price and the advance as a deduction.
It is not enough to cut the amount payable. The client needs the fee and the tax from the advance separately, or its input VAT deduction is wrong. Name the number and date of the advance payment invoice on the final invoice.
What happens if the service is never performed?
Then the client must get the advance back. The cause may be withdrawal (§ 346 BGB) or termination, and the agreement says whether you may deduct costs already incurred. For VAT you correct the tax for the period of the repayment (§ 17 (2) no. 2 UStG), and your client corrects its input VAT deduction.
If you showed tax you do not owe, say because the advance never arrived, the showing itself can trigger tax until you correct the invoice (§ 14c UStG). Correct such invoices with an invoice correction and not by overwriting them.
How do you fix the advance in the contract?
- Amount: a fixed percentage or amount, tied to the total price.
- Due date: a payment term from the invoice, and whether work starts only on receipt.
- Purpose: what the money is needed for, such as third-party costs, so the clause does not read as mere security.
- Credit: that the advance is credited in full against the price.
- Repayment: under which conditions it flows back and what you may deduct.
Where do you lose money on advances?
- The advance is not spotted in the incoming payments, and work starts anyway, without security.
- The final invoice forgets the advance, and the client pays twice or demands repayment and lets the invoice sit.
- The advance invoice shows no tax, and the client later demands a new one, which causes confusion.
- Part of the advance was paid, the rest not, and the final invoice credits the full amount.
- The advance belongs to a contract that later lapses, and nobody refunds it in time.
How does this fit with interim invoices and the milestone plan?
Many projects start with an advance and continue with interim invoices, as the guide to milestones shows. Each step stays a document of its own, and the final invoice settles them all.
30% advance on a campaign
A campaign costs €25,000 net. The contract provides a 30% advance. The client pays it on 3 November 2026, and the campaign is finished in December.
- Advance 30% of €25,000.00Contract, payment plan
- €7,500.00
- VAT 19% on the advance§ 13 (1) no. 1 lit. a sentence 4 UStG
- €1,425.00
- Advance payment invoice, gross
- €8,925.00
The final invoice shows €25,000.00 net and €4,750.00 VAT, €29,750.00 together, and deducts €7,500.00 fee and €1,425.00 tax. The client still pays €17,500.00 plus €3,325.00, so €20,825.00.
How Valtor handles this
Valtor keeps advances as documents of their own, which a final invoice deducts explicitly. Valtor books nothing and does not decide whether an advance is permitted for tax.
Valtor does
- Treats an advance separately from earned milestones, as its own kind of invoice
- Deducts in the final invoice only advances you name explicitly, and only those of the same contract, currency and tax treatment
- Credits only what has actually been paid on the advance, and reconciles net and tax with the approved payment allocations; an unpaid advance gives no deduction
- Credits each advance only once and rejects a final invoice whose deduction exceeds the full price
- Shows the deduction as a line of its own, “Advance received and credited”, with net and tax
You decide
- You decide whether the contract provides for an advance and how it is treated for tax
- You name the advances that are deducted in the final invoice
- You approve and send every invoice
Questions and answers
Is an advance the same as an interim payment?
No. With an advance nothing has been performed yet. With an interim payment (Abschlagszahlung) part of the work is done (§ 632a BGB).
Do I have to issue an advance payment invoice?
The law does not require an invoice for the client to pay. You need one for the client's input VAT deduction, and the VAT arises when the money is received.
May I demand an advance without an agreement?
No. By law the fee falls due after performance. The advance must be in the contract.
Must VAT appear on the advance payment invoice?
If the supply is taxable, yes. The invoice needs the details under § 14 (4) UStG, including rate and tax amount.
When can the client deduct input VAT on the advance?
Once it holds the invoice and has paid the advance (§ 15 (1) sentence 1 no. 1 sentence 3 UStG).
What if the final invoice does not deduct the advance?
Then the client owes too much and the VAT is wrong. You correct the invoice with a correction invoice (Rechnungskorrektur) or cancellation invoice (Stornorechnung).
When must I repay an advance?
If the service is not performed, after withdrawal or termination (§ 346 BGB), minus your costs depending on the contract. You correct the tax under § 17 (2) no. 2 UStG.
This page is general information, not legal or tax advice. Please ask your tax advisor about your own case.