What is a final invoice (Schlussrechnung)?
A final invoice settles the whole service for good and deducts the advances and interim payments the client has already paid (§ 14 (5) UStG).
Last updated:
Key takeaways
- The final invoice always names the full price of the service and deducts everything you billed before.
- Advances and interim payments must be deducted with fee and tax shown separately, or the VAT is wrong.
- In a work contract the final payment falls due only on acceptance, and you issue the invoice at the latest six months after performance.
- A mistake is not overwritten but fixed with a correction invoice or cancellation invoice.
- Valtor calculates the final invoice from the documents you name explicitly and credits only advances that have been paid.
What is a final invoice?
The final invoice is the last invoice for a service you billed in stages. It states the total price, deducts the advances and interim payments already received and demands the rest. It closes the settlement of the contract: afterwards the client will normally assume that everything you wanted to bill has been billed.
The term comes from construction and work-contract law but is used for any staged billing, including fixed-price projects of agencies and consultancies. For VAT purposes it is called the “Endrechnung” (§ 14 (5) sentence 2 UStG). Both words mean the same document.
When do you issue the final invoice, and when does it fall due?
You issue it once the service is fully performed, in a work contract that means with acceptance. Only then does the fee fall due (§ 641 (1) BGB). For a service to another business you must issue the invoice within six months of performing it (§ 14 (2) sentence 1 no. 2 UStG), or a fine can follow (§ 26a UStG).
Then the agreed payment term runs. Without an agreement the final payment is due on receipt of the invoice (§ 271 BGB), and default occurs at the latest after 30 days (§ 286 (3) BGB). The regular limitation period of three years starts at the end of the year in which the claim fell due (§§ 195, 199 (1) BGB). A final invoice never issued therefore does not lapse at once, but it costs liquidity and nerves.
How is a final invoice structured?
- Whole servicefull net price, with VAT
- Deduct advancesper invoice: number, date, fee, tax
- Deduct interim paymentsper invoice: number, date, fee, tax
- Remaining amountfee and tax still open
The structure always follows the same calculation, from the whole to the remainder:
What must a final invoice state?
It is a complete invoice under § 14 (4) UStG and also needs the deductions:
- All mandatory details: names, addresses, tax number or VAT ID, issue date, a consecutive invoice number, and quantity and kind of the service.
- The time of supply or the service period (§ 14 (4) no. 6 UStG), for a work usually the acceptance date.
- The fee by tax rate for the whole service, the rate and the tax amount.
- The partial fees received before the service and the tax on them, deducted (§ 14 (5) sentence 2 UStG).
- For each deduction the number and date of the earlier invoice, so the client can follow the remainder.
- The remaining amount and the payment term.
How does VAT come out right on the final invoice?
The final invoice shows tax on the total price and deducts the tax you already showed in advance and interim invoices. What counts is that you deduct fee and tax separately. Anyone who only cuts the gross amount of the earlier invoices leaves the split in the dark and endangers the client's input VAT deduction.
If the tax rate changed between the advance and the service, the service takes the rate at the time of performance. The advance followed the rate at receipt, and the final invoice corrects the difference. In case of doubt your tax adviser checks when the tax arose.
What does not belong on the final invoice?
The final invoice is not a collection point for open items from other contracts:
- Services under other contracts: they remain invoices of their own.
- Extras the client has not ordered: you need an order or a change request before you bill them.
- Default interest and reminder costs: they are not fees and belong in a letter of their own in dunning.
- Refunds: if the client overpaid, you repay the amount or set it off expressly, instead of cutting it unclearly.
Is there a partial final invoice, and does the final payment rule out further claims?
A partial final invoice settles a distinct part of the service for good, such as a self-contained phase that the contract remunerates separately. It is not an interim invoice, because the part is finished and accepted. Whether it is allowed is for the contract to say, and for VAT it can be a partial supply (§ 13 (1) no. 1 lit. a sentence 3 UStG).
Under the BGB, payment on a final invoice does not rule out further claims. Under VOB/B contracts the effect of the final payment applies instead: whoever accepts the final payment without reservation can claim further only within narrow limits (§ 16 (3) VOB/B). Outside the VOB such an exclusion is in the contract only if expressly agreed. Still, check before sending that the final invoice really contains everything, because a later claim costs credibility and time.
How do you correct a wrong final invoice?
You do not overwrite an issued invoice. If mandatory details are missing or wrong, you supplement or correct them in a document that refers specifically to the original invoice (§ 31 (5) UStDV). If the amount or tax is wrong, you correct with an invoice correction or a cancellation invoice and issue a new one.
If the final invoice shows too much tax, you owe the higher amount until you correct it (§ 14c (1) UStG). That is a frequent reason to keep deductions clean. The guide on correcting an invoice shows the steps.
Where do you lose money on the final invoice?
- The final invoice is never issued because nobody reports the end of the project, and the final payment arrives months later.
- An advance is deducted twice, and you give the client money.
- An advance is not deducted, the client overpays or disputes the invoice and holds it.
- The deduction follows the invoice, not the incoming payment. If only part was paid, the deduction is too high.
- The final invoice goes out before acceptance, and the client rejects it.
final invoice after an advance and an interim payment
A project costs €50,000 net. The client has paid an advance (€11,900.00 gross, of which €10,000.00 fee) and an interim payment (€17,850.00 gross, of which €15,000.00 fee). The project is accepted on 20 November 2026.
- Whole service, feeContract
- €50,000.00
- less advance payment invoice of 3 September 2026, fee§ 14 (5) sentence 2 UStG
- −€10,000.00
- less interim invoice of 15 October 2026, fee§ 14 (5) sentence 2 UStG
- −€15,000.00
- VAT 19% on the remaining €25,000.00 (€9,500.00 less €1,900.00 and €2,850.00)§ 12 (1) UStG
- €4,750.00
- Remaining amount, gross
- €29,750.00
The whole invoice comes to €59,500.00. Of that, €11,900.00 and €17,850.00 are paid, which leaves €29,750.00.
How Valtor handles this
Valtor calculates a final invoice from the whole service and the documents you name explicitly. Valtor books nothing and does not hunt for earlier invoices on its own.
Valtor does
- Calculates the final invoice from the stated total price and the named advances and deposits, and deducts each as a line of its own with fee and tax
- Never discovers earlier invoices from the contract alone and credits only what is named
- Requires a reason and your confirmation that you reviewed the earlier documents before a final invoice is created
- Tracks money received per document and credits only what has been paid and not yet applied, so partial payments come out right
- Rejects double deductions, documents that are not issued or are cancelled, and deductions above the total price
You decide
- You name the documents that are deducted and confirm you reviewed them
- You decide whether advances and interim payments count for tax as advances or partial supplies
- You approve and send the invoice
Questions and answers
Must the final invoice list the instalments one by one?
Yes, with invoice number, date and amount. Only then can the client follow the remainder.
What if the final invoice was wrong?
You do not overwrite it. You correct it with a correction invoice (Rechnungskorrektur) or cancellation invoice (Stornorechnung) that refers to the original invoice.
By when must I issue the final invoice?
For services to businesses within six months of performance (§ 14 (2) sentence 1 no. 2 UStG). The claim becomes time-barred after three years from the end of the year it fell due.
Is Schlussrechnung the same as Endrechnung?
Yes. The VAT Act speaks of the Endrechnung (§ 14 (5) sentence 2 UStG), in daily use people say Schlussrechnung.
Must I deduct the VAT of the advance separately?
Yes. Fee and tax are deducted separately, or VAT and the input VAT deduction do not match.
When does the final payment fall due?
In a work contract with acceptance (§ 641 (1) BGB), then per the agreed payment term, otherwise on receipt of the invoice (§ 271 BGB).
What if the client paid only part of the advance?
Then you deduct only the part paid. The unpaid remainder stays open. Valtor credits only what has been paid and released.
This page is general information, not legal or tax advice. Please ask your tax advisor about your own case.