# What is time and materials (Aufwandsabrechnung)?

URL: https://valtor.io/en/glossary/time-and-materials
Language: en
Last updated: 2026-11-10

With time and materials the client pays for the effort actually spent, usually hours or days at an agreed rate, instead of a fixed amount.

## Key takeaways

- The price arises only afterwards, from rate times actual effort. The volume risk lies with the client, the risk of proof with you.
- What you cannot prove you do not get paid in a dispute. A prompt timesheet with a description of the work is therefore part of the business.
- Billing increments, rounding, travel time and minimum blocks belong in the contract, because they change every invoice.
- An estimate is not binding, an agreed maximum is a limit. Whoever confuses the two loses the hours above the cap.
- In Valtor the amount arises only from an accepted quantity. If it is missing, the invoice waits, and Valtor never estimates.

## What is time and materials?

With time and materials (Aufwandsabrechnung) you bill the effort actually spent: hours or days times rate, plus expenses and materials where needed. The total is known only when the work is done. It is the counterpart to the [flat fee](https://valtor.io/en/glossary/flat-fee) and the [fixed-price contract](https://valtor.io/en/glossary/fixed-price-contract), where the price is fixed in advance.

The model fits when the scope is unclear at the start or changes: advisory work, development, agile projects, support. It is fair because each side pays or delivers only what actually accrues. It has two weaknesses: the client has no fixed budget, and you carry the effort of documentation.

## What is the legal basis for billing by effort?

Usually it is the form of payment of a service contract (§ 611 BGB): you owe your time and care, not a result. The fee follows the agreement, and without a price agreement the customary one applies (§ 612 (2) BGB). In a contract for work by effort, such as development at an hourly rate, you do owe the result, and the due date hangs on acceptance (§ 641 BGB). The contract should say which applies.

Under the statutory model the fee in a service contract is payable after the services are rendered (§ 614 BGB), and where measured by periods of time at the end of each period. Monthly billing in arrears matches that. The invoice must carry the service period (§ 14 (4) sentence 1 no. 6 UStG) and the type and extent of the service (no. 5): with hourly billing that means the hours and the rate.

## What must the contract regulate for time and materials?

Almost every dispute about hourly invoices has its cause in a gap at this point:

- The rates by role and seniority, and their validity period, see [framework agreement](https://valtor.io/en/glossary/framework-agreement).
- The billing increment: is billing exact to the minute, in 15-minute blocks or in half hours, and how is it rounded?
- Travel time, set-up time and waiting time: are they charged at the full rate, a reduced rate or not at all?
- The proof: in what form and how often do you submit time, and how long does the client have to object?
- Estimate and maximum: is a figure only a forecast or a limit?
- Expenses and materials, with or without a markup, and from what amount the client approves them in advance.
- Payment term and invoicing rhythm, for example monthly at month end.

## How do you prove the effort?

In a dispute the service provider in principle carries the burden of setting out performance and extent. That works with a timesheet that contains date, duration, person and an understandable description of the activity. An entry “project work, 8 hrs” convinces less than “navigation structure concept, alignment with Ms Berger, 3.5 hrs”. Record promptly: hours reconstructed a week later are open to attack.

Attach the proof to the invoice or make it available for inspection, and agree a period after which it counts as approved, say 14 days. What the proof can look like is shown in the [proof-of-service template](https://valtor.io/en/proof-of-service-template), see also [proof of service](https://valtor.io/en/glossary/proof-of-service).

## How do you bill, and what belongs on the invoice?

Example with three roles for one month. Senior advisory: 14 hours at €150 = €2,100.00. Development: 62 hours at €110 = €6,820.00. Project management: 8 hours at €125 = €1,000.00. Together €9,920.00 net, plus travel per receipt of €380.00 makes €10,300.00. With 19% VAT of €1,957.00 that is €12,257.00 gross.

The invoice shows hours and rate per role, the service period and the expenses. Expenses that you lay out in the name and for the account of the client and that merely pass through are not part of the consideration (§ 10 (1) sentence 6 UStG). Passed-on own costs, by contrast, count as taxable consideration. The distinction is demanding, so clarify it in advance with your tax adviser.

## How do billing increments and rounding affect the bill?

The increment changes the invoice more than one expects. Example: 20 entries of 10 minutes each make 200 minutes, that is 3 hours 20 minutes. At a rate of €110 that is €366.67. If every entry is rounded up to 15 minutes, it is 20 × 15 minutes = 300 minutes = 5 hours and €550.00.

Here rounding raises the bill by half. That can be agreed, but with short entries it is hard for the client to follow, and in pre-formulated terms it may not withstand the fairness review (§ 307 BGB). Choose an increment you can explain to the client, and write it into the contract.

## How do effort without a cap, with a cap and with an hour bank differ?

Effort is not the same as effort. The variant decides who carries which risk.

## What applies to a maximum or an estimate?

An estimate, in the statute a cost estimate (§ 649 BGB), is not binding without a guarantee. If costs exceed it substantially, the client may in some circumstances terminate and then owes only the work done until then. An agreed maximum, by contrast, is a limit on your fee. Example: the cap is €12,000.00 net, the effort €13,150.00. Billable is €12,000.00, the remaining €1,150.00 stays unpaid as long as the cap is not raised.

So watch consumption. Tell the client in writing at 80% that the cap is near, and obtain an increase before you continue. What you do afterwards is otherwise not ordered.

## Where does time go unpaid under time and materials?

- Hours are not recorded. If 5 hours a week per person are missing at a €110 rate over 46 weeks, that is €25,300.00 net a year.
- The time is there, but the invoice goes out months later. Claims become time-barred in three years at year end (§§ 195, 199 BGB), and the longer you wait, the harder the proof.
- The cap is exceeded without anyone raising it.
- Travel time and expenses are not in the contract and are not billed out of uncertainty.
- A client approval is missing, and the invoice is rejected although the time is right.
- The rate is out of date: a new rate applies in the framework, and the invoice names the old one.

## Worked example: one month by effort

A client pays by effort. In the month three roles accrue, plus travel per receipt.

| Position | Betrag / Amount |
| --- | --- |
| Senior advisory: 14 hrs × €150.00 (Framework, senior rate) | €2,100.00 |
| Development: 62 hrs × €110.00 (Framework, development rate) | €6,820.00 |
| Project management: 8 hrs × €125.00 (Framework, PM rate) | €1,000.00 |
| Travel per receipt (Framework, expenses) | €380.00 |
| **Sum, net** | **€10,300.00** |

With 19% VAT (€1,957.00) that is €12,257.00 gross. The invoice shows hours, rate and the service period for each role.

## How Valtor handles this

Valtor calculates from the accepted quantity and waits when it is missing.

Valtor does:
- Calculates each usage-based line from the accepted figures, quantity times rate, where needed with tiers and a minimum and maximum per period
- Asks the responsible person for their figure every period and reminds them before the invoice date; escalation follows the responsibility on file
- Never estimates for an invoice: if a quantity is missing, the invoice waits. A preview may show a forecast, marked as a forecast
- Where wanted, shows the client in the portal the accepted quantity to confirm. Confirmation or objection holds no invoice
- Flags when an amount would exceed an agreed cap

You decide:
- You assign each line to a person who enters the quantities
- The finance team accepts every figure before it reaches an invoice
- You set billing increment, rounding and travel time in the contract
- You approve and send every invoice

Calendar from the contract, e-invoicing, approval and sending kept apart. [See Valtor Billing](https://valtor.io/en/product/billing)

### What does time and materials mean?

Billing by the effort actually spent, usually hours or days at the agreed rate, plus expenses and materials. In German Aufwandsabrechnung.

### Do I have to keep a timesheet?

Not expressly by statute, but in a dispute you carry the burden of proving performance and extent. Keep it promptly, with the activity, and attach it to the invoice.

### May I bill beyond a stated amount?

For a non-binding estimate yes, if the effort actually arose. For an agreed maximum no, without raising the cap.

### May I charge travel time?

Only if the contract provides for it or it is customary. Agree expressly whether and at what rate it is charged.

### Are expenses subject to VAT?

Own costs you pass on are part of the consideration and carry VAT. Only genuine pass-through items under § 10 (1) sentence 6 UStG do not. Clear it with your tax adviser.

### How often should I bill by effort?

Usually monthly at month end, in short projects per phase. The shorter the interval, the easier the proof and the sooner the money flows.

### When is effort better than a fixed price?

When the scope is unclear at the start or changes, as in agile development or advisory work. Then the client carries the volume risk and not you.