# What is acceptance (Abnahme)?

URL: https://valtor.io/en/glossary/acceptance
Language: en
Last updated: 2026-11-10

Acceptance is the client's declaration that it takes a finished work as essentially conforming to the contract; with it the fee falls due (§§ 640, 641 BGB).

## Key takeaways

- Acceptance exists only in a work contract (Werkvertrag), where a result is owed. In a service contract such as a retainer there is none.
- With acceptance the fee falls due, the warranty period starts and the risk passes to the client.
- The client may not refuse acceptance for insignificant defects, and after a deadline you set it can be deemed given.
- Money stays on the table when acceptance sits in an email that never reaches billing.
- Valtor holds a milestone tied to acceptance and makes it billable only after the evidence has been checked.

## What is acceptance, and where does it exist?

Acceptance means the client takes the finished work as essentially performance in line with the contract. The law requires it of the client as far as the nature of the work allows (§ 640 (1) sentence 1 BGB). It has two parts: physically taking the work, and the declaration that it is in order in substance.

Acceptance belongs to the work contract. A website, a concept, a campaign or an expert report are results one can accept. Under a service contract (Dienstvertrag) you owe an activity instead, such as the monthly support in a [retainer](https://valtor.io/en/glossary/retainer). There is nothing to accept there, and the fee follows the end of the agreed period. Whether a contract is a work or service contract depends on what it says, not on its title.

## What are the legal effects of acceptance?

Acceptance is the turning point of a work contract. Several effects occur at once, and each matters for your billing:

## How does acceptance work in practice?

A fixed sequence that the contract describes helps. Without one, parties argue later whether acceptance happened at all:

## When is a work deemed accepted without an express declaration?

In two cases. First, the client plainly takes the work as performance, for example by publishing the website or using the software productively without objecting to the fee (acceptance by conduct). Second, after completion you can set the client a reasonable deadline for acceptance. If it does not refuse within that deadline, naming at least one defect, the work is deemed accepted (§ 640 (2) sentence 1 BGB).

Against a consumer the second rule applies only if you pointed out the consequences in text form with the request (§ 640 (2) sentence 2 BGB). About two weeks is usually reasonable for a simple work, and large projects need more. Set the deadline in writing and have the receipt confirmed.

## May the client refuse acceptance?

Not because of insignificant defects (§ 640 (1) sentence 2 BGB). The defects remain as a warranty claim, but the fee falls due. A significant defect that impairs the purpose of the work allows refusal. Then you must rectify and call the client to accept again.

A court draws the line in a dispute, so a defect classification in the contract pays off: what is a blocker, what is a small fault. The client may withhold a part of the fee that stands in reasonable proportion to the cost of rectifying defects, usually double the cost (§ 641 (3) BGB).

## What belongs in the acceptance clause and the acceptance protocol?

- Subject: which work or part is accepted, with a reference to the specification.
- Form: in writing, in text form or by protocol, and who may sign for the client.
- Deadline: the review period in calendar days and the effect of silence, that is deemed acceptance.
- Defects: a split into significant and insignificant defects and the procedure for rectification.
- Partial acceptance: whether it is provided for, for which parts, and which share of the payment hangs on which acceptance.
- Protocol: date, attendees, the accepted work, reservations and signatures of both sides.

## What does acceptance mean for VAT and the invoice?

For VAT purposes a work is generally performed only on acceptance. The tax arises at the end of the advance-return period in which the supply was made (§ 13 (1) no. 1 lit. a sentence 1 UStG). If you received money earlier, the tax arises to that extent with receipt (sentence 4).

You must invoice a business within six months of performing the service (§ 14 (2) sentence 1 no. 2 UStG), and breaches can be a regulatory offence (§ 26a UStG). The invoice states the time of supply (§ 14 (4) no. 6 UStG), for a work the acceptance date. Payments before acceptance are advances or instalments that the [final invoice](https://valtor.io/en/glossary/final-invoice) must deduct.

## Where do you lose money around acceptance?

Most losses are organisational, not legal:

- Acceptance sits in an email with the project lead, and billing never hears of it. The milestone stays unbilled for weeks.
- The invoice goes out before acceptance. The client rejects it, and the [payment term](https://valtor.io/en/glossary/payment-term) does not start.
- A partial acceptance is not documented apart from the final acceptance, and nobody knows what is due.
- The deadline for deemed acceptance is never set, and a quiet project stays unaccepted for months.
- The contract names no authorised signatory, and the client later disputes the intern's acceptance.

## How does milestone billing connect with acceptance?

How acceptance and a payment plan fit together is covered in the guide on [acceptance in milestone invoices](https://valtor.io/en/acceptance-milestone-invoice). Anyone who wants to bill parts of the work earlier needs an [interim invoice](https://valtor.io/en/glossary/interim-invoice), which does not replace acceptance. For the payment plan as a whole see [milestone billing](https://valtor.io/en/milestone-billing).

## Worked example: milestone with partial acceptance

A fixed-price project of €48,000 net provides 40% on acceptance of the development phase, that is €19,200.00 net. The contract allows acceptance in parts. On 12 November 2026 the client accepts parts worth €14,400.00 net; the rest still has defects.

| Position | Betrag / Amount |
| --- | --- |
| Accepted part of the milestone (the remaining €4,800.00 net follows after rectification) (Contract, payment plan) | €14,400.00 |
| VAT 19% (§ 12 (1) UStG) | €2,736.00 |
| **Invoice total, gross** | **€17,136.00** |

For the remaining €4,800.00 net, VAT of €912.00 follows later, €5,712.00 together. Both invoices add up to €22,848.00, the gross amount of the milestone.

## How Valtor handles this

Valtor reads acceptance from the contract as the condition of a milestone and holds it until the evidence is on file and a person has checked it. Valtor books nothing and releases nothing itself.

Valtor does:
- Reads the payment plan and milestones from the contract, each value with clause and page, and marks a milestone with acceptance as waiting for evidence
- Gives the client a secure link in the client portal to confirm acceptance and upload a document; the document is filed with the contract
- Makes the milestone billable as soon as a person has confirmed the evidence as checked
- Splits a waiting milestone on request into an accepted part and a remainder that keeps waiting
- Records every step in the audit log: who uploaded, confirmed or split, and when

You decide:
- You check that the document really is an acceptance and confirm it
- You decide whether and how much a partial acceptance counts
- You set the client a deadline for acceptance; Valtor does not deem acceptance
- You approve and send every invoice

Calendar from the contract, e-invoicing, approval and sending kept apart. [See Valtor Billing](https://valtor.io/en/product/billing)

### Can the client refuse acceptance because of minor defects?

No. It may not refuse acceptance for insignificant defects (§ 640 (1) sentence 2 BGB). The defects remain as a warranty claim and the fee falls due.

### Does a retainer need acceptance?

No. A retainer is usually a service contract. The activity is owed, and the fee follows the agreed period.

### Is an email enough as acceptance?

Yes, if the contract demands no stricter form and the content is clear. A reply like “looks good” is risky. A statement that names the work and declares acceptance is better.

### What happens if the client does not react at all?

You set a reasonable deadline. If it does not react and names no defect, the work is deemed accepted (§ 640 (2) BGB). Against consumers only with a notice in text form.

### When do warranty claims become time-barred?

From acceptance: two years for most works, five for buildings (§ 634a (1) and (2) BGB). Without acceptance the period does not start.

### Is an interim invoice allowed before acceptance?

Yes, if the contract provides for it or § 632a BGB applies. It remains a payment on parts of the performance, and acceptance is still to come.

### Can I bill a milestone without acceptance?

Only if the payment plan does not tie it to acceptance. If the amount hangs on acceptance, it falls due with it. Valtor holds it until the evidence is checked.